Project Description

Canonbury Square

KLT was awarded this major project to replace the last Donkin Reynolds type governor still functional within the city of London, supplying gas to >50,000 customers.

The works included the installation of a new 36” quad stream below ground unit, the installation of 800mm PE & 900mm steel MP/LP PE mains, live connections to the 42” MP and 36” LP mains and disconnection of the existing R6 below ground governor.

Construction began on the first of April 2019. Customer and Environmental plans formed a key part of the construction plan, ensuring there were no ecological impacts from the project. Care was taken to reduce traffic movements and manage these as not to impact our customers.

The project was successfully completed on time while meeting our clients and exceeding our customers expectations.

Project Details

Client

Cadent

Project Type

Gas Maintenance Replacement