HS2 Gas Diversion Project, West Gate (Ealing)
The Murphy Group contracted KLT Utilities to deliver complex gas main diversion works as part of the HS2 infrastructure programme.
At West Gate in Ealing, KLT replaced 900 metres of 18-inch medium-pressure cast iron main using a combination of open cut and insertion methods. The works were split into two main sections: in the north, DN500 and DN400 PE mains were installed along West Gate and through the Vent Shaft compound; in the south, a DN400 PE main crossed the A40, with works extending from Lynwood Road to Brunswick Road. Throughout, maintaining gas supply to a key District Governor and multiple industrial off-takes required meticulous planning and sequencing.
A critical engineering challenge involved replacing 100 metres of gas main beneath the heavily trafficked A40. This section demanded a robust traffic management strategy to mitigate disruption and ensure public and workforce safety.
The project demonstrated KLT’s ability to execute technically demanding works within a live urban network, balancing operational delivery with stakeholder impact.